DIMM PERMANENT MOUNTING

INTERFACE TASKS

Version 1.0 April 17, 2001

These are the inter-institutional communications needed to finish the DIMM permanent mounting.


Line

Item

From->To

Status

Notes

1

Bandpass specifications for water vapor filters.

J. Gunn->A. Uomoto


JHU will handle filter acquisition, but separately from DIMM permanent mounting program.

2

Precise location for lightning-protected UPS AC line power.

G. Scharfstein->F. Leger


Wire termination inside DIMM enclosure via conduit; same conduit carries network fiber optics.

3

Notification of delivery of lightning-protected UPS AC line power.

F. Leger->G. Scharfstein



4

Specific location for fiber optic ethernet (note this must be the same as UPS AC line power if conduit is shared).

G. Scharfstein->C. Loomis


Termination inside DIMM enclosure via conduit; same conduit carries AC line power.

5

Notification of delivery of live fiber optic ethernet.

C. Loomis->G. Scharfstein


ST connectors, mutlimode fiber, Fast Ethernet. Will there be spares?

6

Specific location and fittings for glycol cooling line.

G. Scharfstein->F. Leger



7

Notification of delivery of glycol cooling line.

F. Leger->G. Scharfstein



8

Specification of bolt pattern at mounting location.

G. Scharfstein->F. Leger



9

Installation of mounting fixtures specified above.

F. Leger->G. Scharfstein


JHU supplies mounting hardware and special tools

10

Specific controls configuration.

G. Scharfstein->A. Rest



11

Delivery, training, and handoff.

G. Scharfstein->F. Leger